Defining the WBS Work (Breakdown Structure)
A WBS is a hierarchy of work that must be accomplished to complete a project, which defines a product or service to be produced. Technical Data used in the field explained in primavera p6 training in Islamabad. The WBS is structured in levels of work detail, beginning with the deliverable itself, and is then separated into identifiable work elements.
Each project has its own WBS hierarchy with the top level WBS element being equal to that of each EPS node (on page 813) or project. Each WBS element may contain more detailed WBS levels, activities, or both.
When creating a project, the project manager typically develops the WBS first, assigns documents to each WBS element, and then defines activities for performing the element's work. In addition to document and activity assignments, each WBS element also has an assigned calendar, specific earned value calculation settings, and an assigned OBS element responsible for all work included in the WBS element. Some more details of primavera p6 training in Islamabad are as under.
Using a WBS at the planning stages of a project is beneficial for summary rollups of data not yet associated with projects.
The WBS hierarchy can contain anticipated dates, planned budgets, and summary values. Financial information is used interchangeably between projects and their WBS elements, so you can use the pre-established budget amounts and funding information you set for WBS elements immediately for their project and activity counterparts. The budget and spending plan can stand alone to represent financial data for the WBS level, or it can reflect the budget distribution data established for the project. Summary information can be rolled up to any WBS level you specify. TSK Training for Skills and Knowledge is the best institute in Rawalpindi Islamabad for Pakistani Students who wants to join primavera p6 training in Islamabad.