Activities are the fundamental work elements of a project. They are the lowest level of a work breakdown structure (WBS) and, as such, Technical Data used in the field explained in primavera p6 training in islamabad, are the smallest subdivision of a project that directly concerns the project manager. Although you can divide activities into steps, an activity's primary resource is typically responsible for managing and tracking the progress of an activity's steps, while the project manager is typically responsible for managing and tracking the progress of the overall activity.

You can define the following information for an activity:

Activity ID and name, which enables you to uniquely identify and describe the activity, Activity start and finish dates, Activity calendar, Activity type, duration type, and percent complete type, which are used to specify which calendar applies to an activity; whether an activity is a milestone; how to keep an activity's unit values, duration values, and resource units/time values synchronized; and how to calculate an activity's percent complete, Activity codes and values, which enable you to classify and categorize activities, Constraints on the activity's scheduled start and finish dates, Expenses, Predecessor and successor relationships, which are used to define relationships with other activities. Some more details of primavera p6 training in Islamabad are as under.

P6 Professional automatically synchronizes the duration, labor/ no labor units, and resource units/time for activities so that the following equation is always true for each activity:

Duration = Units ¸ (Resource Units ¸ Time)

However, since three variables are involved (duration, units, and resource units/time), when you change the value of one variable, P6 Professional must alter the value of a second to balance the equation. The Duration Type setting for an activity allows you to control how P6 Professional synchronizes these variables when any one of the equation's variables is changed. TSK Training for Skills and Knowledge is the best institute in Rawalpindi Islamabad for Pakistani Students who wants to join primavera p6 training in Islamabad.